By Leslie
Gatpolintan
MANILA -- Listed
PetroEnergy Resources Corp. (PERC) said on Monday the expansion project at the
Maibarara geothermal power plant in Santo Tomas,
Batangas is currently being
finished to meet target commercial operation this December.
Maibarara
Geothermal Inc. (MGI) plant manager Paul Morala said the commissioning and
testing of the 12-megawatt Maibarara-2 now “enter their final phases.”
PERC told the
local bourse that MGI's 20-MW Unit-1 reached its 600-gigawatt hour (GWh)
generation mark during the billing period ending Oct. 25, a milestone achieved
more than three years from the start of the facility’s commercial operation.
“Apart from the scheduled annual maintenance
shutdowns, we have managed to minimize forced outages in the facility leading
to very high capacity and availability factors,” said MGI President Francisco
Delfin Jr.
The Maibarara-1
plant was recently declared as the Best Renewable Energy Project in the
national grid category of the ASEAN Energy Awards 2017 held during the ASEAN
Energy Ministers Meeting in Manila last September.